The US Federal Communications Commission’s Space Bureau on Wednesday 25 November 2026 issued a Memorandum Opinion, Order and Authorization, DA 26-1273, granting in part and with conditions SpaceX’s application to deploy Starmind, an orbital data-center system of up to one million satellites in low Earth orbit. The text of the order is in the Commission’s attachment. The applicant is named in the order as Space Exploration Holdings, LLC.
Key takeaways
- The FCC’s Space Bureau on 25 November 2026 issued a Memorandum Opinion, Order and Authorization (DA 26-1273) granting, in part and with conditions, SpaceX’s application to deploy the Starmind constellation of up to one million satellites as orbital data centers.
- The order says the authorization becomes null and void unless one satellite is deployed by 25 November 2033, 10% of the authorized maximum by 25 November 2035, 50% by 25 November 2038, and the authorized constellation is completed by 25 November 2040.
- It places the satellites at altitudes from 500 to 1,002 km, says communications will rely on optical links, and authorizes Ka-band frequencies only for backup and emergency telemetry, tracking and command.
The BBC described the decision as the first approval of its kind. Gulf News, citing Agence France-Presse, wrote that the FCC on Wednesday authorized SpaceX to launch up to one million satellites as part of its plan to build data centers in space.
What the order authorizes
The order names the system Starmind and describes a constellation of 1,000,000 satellites to be deployed into orbital shells each spanning 50 km, at altitudes from 500 to 1,002 km, in 30-degree inclinations and sun-synchronous inclinations.
The scope of the grant is radiofrequency communications for backup and emergency telemetry, tracking and command. The order says Starmind will rely on optical links for communications, and that Ka-band frequencies — 18.8–19.3 GHz (space-to-Earth) and 28.6–29.1 GHz (Earth-to-space) — are authorized only for backup and emergency use, on an unprotected and non-interference basis.
Conditions and deadlines
The grant is marked “GRANTED-IN-PART/DEFERRED-IN-PART – With Conditions.” It says the authorization becomes null and void unless the stations are deployed and operated as follows: one authorized space station no later than 25 November 2033; 10% of the maximum number of authorized space stations by 25 November 2035; 50% by 25 November 2038; and the remaining stations needed to complete the authorized constellation by 25 November 2040.
The license term is 15 years. It begins at 3 a.m. Eastern Time on the date SpaceX certifies to the Commission that the first Starmind satellite has been placed into orbit and that its operations fully conform to the authorization.
The Bureau deferred SpaceX’s request for a waiver of the rule that satellites ending their mission below 2,000 km be disposed of by atmospheric re-entry. Before deploying or operating any Starmind satellites that will not be disposed of that way, the company must apply to modify the authorization and provide sufficient justification for any waiver.
What the reports add
The BBC quotes FCC Chairman Brendan Carr as saying the decision “opens a bold new frontier for the computing infrastructure needed to power America’s leadership and growth,” and that “this is the kind of American ingenuity that can unite our strengths in space and advanced technology, reinforce our economic leadership, and expand prosperity here at home.”
The BBC also reported that Elon Musk replied to the announcement on X: “Much appreciated. This will be a great asset to America and the world.”
Gulf News, citing AFP, said Musk in August promised a first launch into orbit in the fourth quarter of 2027 and a ramp-up in 2028. The BBC wrote that the company has said it wants to launch its first Starmind satellite next year.
Gulf News reported that SpaceX has struck a deal with Nvidia to supply its latest-generation Vera Rubin processors, designed to operate in space, and that Starmind satellites will communicate with the Starlink network, which will then relay the data to Earth. The BBC wrote that Starlink already has more than 10,000 satellites, and that Starmind’s satellites will communicate with them and then relay the data to Earth.
Gulf News said projects for orbiting data centers have multiplied since last year: Google is pursuing work under the codename Suncatcher, Blue Origin has filed with the FCC for Project Sunrise, Starcloud operated an advanced GPU aboard a satellite in late 2025, and Google also did so in October.
The BBC wrote that it is unclear whether a million satellites will actually be launched, or whether SpaceX has sought approval for a higher number than it will use. An expert previously told the BBC that launching hardware into orbit remains expensive and that the infrastructure to protect, cool and power it can be complex, while another cautioned that a growing number of low-orbit craft increases the possibility of collisions. Gulf News said not all the technical challenges have been resolved, including processors’ ability to withstand high levels of radiation in space, extreme temperatures, and damage from space debris and micrometeorites.
The BBC also wrote that the approval comes as communities across the United States have pushed back against the expansion of data centers on the ground.
Why it matters for the Gulf
Wednesday’s FCC order does not mention any project in the Gulf.
The region is already building large terrestrial AI compute campuses. On 22 May 2025, G42 and the Abu Dhabi Media Office announced Stargate UAE, a 1-gigawatt compute cluster in the 5-gigawatt UAE–US AI Campus in Abu Dhabi, to be built by G42 and operated by OpenAI and Oracle. On 9 November 2026, HUMAIN announced financing agreements with the National Infrastructure Fund of up to SAR 2.5 billion to support AI computing deployment and critical power infrastructure in Saudi Arabia, including for HUMAIN’s AI data centers.
The BBC wrote that SpaceX presents orbital data centers as the most cost- and energy-efficient way to meet demand for AI computing beyond terrestrial capabilities, at a time of local opposition in the United States to ground facilities. Gulf News reported that a satellite in sun-synchronous orbit can capture solar energy continuously and with eight times the efficiency of its ground-based equivalent, according to that report. Those figures are the report’s, not an independent measurement of our own.
On 20 November, US President Donald Trump said he would impose a “tremendous tax” on companies that build data centers outside America, The National reported. Wednesday’s order does not tie those remarks to any named Gulf project.